beabigegg 2d80a8384e feat: implement custom fields, gantt view, calendar view, and file encryption
- Custom Fields (FEAT-001):
  - CustomField and TaskCustomValue models with formula support
  - CRUD API for custom field management
  - Formula engine for calculated fields
  - Frontend: CustomFieldEditor, CustomFieldInput, ProjectSettings page
  - Task list API now includes custom_values
  - KanbanBoard displays custom field values

- Gantt View (FEAT-003):
  - TaskDependency model with FS/SS/FF/SF dependency types
  - Dependency CRUD API with cycle detection
  - start_date field added to tasks
  - GanttChart component with Frappe Gantt integration
  - Dependency type selector in UI

- Calendar View (FEAT-004):
  - CalendarView component with FullCalendar integration
  - Date range filtering API for tasks
  - Drag-and-drop date updates
  - View mode switching in Tasks page

- File Encryption (FEAT-010):
  - AES-256-GCM encryption service
  - EncryptionKey model with key rotation support
  - Admin API for key management
  - Encrypted upload/download for confidential projects

- Migrations: 011 (custom fields), 012 (encryption keys), 013 (task dependencies)
- Updated issues.md with completion status

🤖 Generated with [Claude Code](https://claude.com/claude-code)

Co-Authored-By: Claude Opus 4.5 <noreply@anthropic.com>
2026-01-05 23:39:12 +08:00

3.3 KiB
Raw Blame History

Proposal: Add Gantt View

Change ID: add-gantt-view Issue Reference: FEAT-003 (issues.md) Status: Draft Author: Claude Date: 2026-01-05

Summary

實作甘特圖視角,以時間軸方式呈現專案任務,顯示任務期間、依賴關係和里程碑。

Motivation

甘特圖是專案管理的核心視覺化工具,可幫助團隊:

  • 了解任務時程與排程
  • 識別關鍵路徑
  • 發現資源衝突和瓶頸
  • 追蹤進度與延遲

目前系統僅有看板和列表視角,缺少時間軸視圖,無法直觀地規劃和追蹤專案進度。

Scope

In Scope

  • Backend: Task model 新增 start_date 欄位
  • Backend: TaskDependency model前置任務關係
  • Backend: 依賴關係 CRUD API
  • Frontend: Gantt chart 元件(使用第三方函式庫)
  • Frontend: 任務時程編輯(拖拉調整日期)
  • Frontend: 依賴關係視覺化(箭頭連線)

Out of Scope

  • 關鍵路徑計算
  • 資源分配視圖
  • 基線對比功能
  • 匯出為圖片/PDF

Design Decisions

任務依賴類型

Type 說明 範例
finish_to_start (FS) 前置任務完成後才能開始 設計完成 → 開發開始
start_to_start (SS) 前置任務開始後才能開始 設計開始 → 文件開始
finish_to_finish (FF) 前置任務完成後才能完成 開發完成 → 測試完成
start_to_finish (SF) 前置任務開始後才能完成 較少使用

預設: finish_to_start (FS) 為最常見類型

Data Model 變更

-- Task 新增欄位
ALTER TABLE pjctrl_tasks ADD COLUMN start_date DATETIME;

-- 新增依賴關係表
CREATE TABLE pjctrl_task_dependencies (
  id UUID PRIMARY KEY,
  predecessor_id UUID REFERENCES pjctrl_tasks(id),
  successor_id UUID REFERENCES pjctrl_tasks(id),
  dependency_type ENUM('FS', 'SS', 'FF', 'SF') DEFAULT 'FS',
  lag_days INT DEFAULT 0,
  created_at TIMESTAMP
);

前端函式庫選擇

建議使用 DHTMLX GanttFrappe Gantt

函式庫 優點 缺點
DHTMLX Gantt 功能完整、效能好 商業授權
Frappe Gantt 開源、輕量 功能較少
React-Gantt-Chart React 原生 社群較小

建議: 使用 Frappe GanttMIT 授權),足夠基本需求

API 設計

# 依賴關係 API
POST   /api/tasks/{task_id}/dependencies         # 新增依賴
GET    /api/tasks/{task_id}/dependencies         # 取得依賴
DELETE /api/task-dependencies/{dependency_id}   # 刪除依賴

# 任務日期更新(使用現有 API
PUT    /api/tasks/{task_id}                      # body 包含 start_date, due_date

日期驗證規則

  • start_date 不可晚於 due_date
  • 有依賴關係時,根據 dependency_type 驗證日期合理性
  • 循環依賴檢測

Affected Specs

Spec Change Type
task-management MODIFIED (Multiple Views requirement 甘特圖細節)

Risks & Mitigations

Risk Mitigation
複雜依賴關係影響效能 限制單任務最多 10 個直接依賴
循環依賴 新增/修改依賴時進行循環檢測
大型專案載入慢 分頁載入或虛擬滾動

Dependencies

  • Frappe Gantt或其他甘特圖函式庫
  • 需要 Task model 已有 due_date 欄位(✓ 已存在)