- Custom Fields (FEAT-001): - CustomField and TaskCustomValue models with formula support - CRUD API for custom field management - Formula engine for calculated fields - Frontend: CustomFieldEditor, CustomFieldInput, ProjectSettings page - Task list API now includes custom_values - KanbanBoard displays custom field values - Gantt View (FEAT-003): - TaskDependency model with FS/SS/FF/SF dependency types - Dependency CRUD API with cycle detection - start_date field added to tasks - GanttChart component with Frappe Gantt integration - Dependency type selector in UI - Calendar View (FEAT-004): - CalendarView component with FullCalendar integration - Date range filtering API for tasks - Drag-and-drop date updates - View mode switching in Tasks page - File Encryption (FEAT-010): - AES-256-GCM encryption service - EncryptionKey model with key rotation support - Admin API for key management - Encrypted upload/download for confidential projects - Migrations: 011 (custom fields), 012 (encryption keys), 013 (task dependencies) - Updated issues.md with completion status 🤖 Generated with [Claude Code](https://claude.com/claude-code) Co-Authored-By: Claude Opus 4.5 <noreply@anthropic.com>
This commit is contained in:
111
openspec/changes/archive/2026-01-05-add-gantt-view/proposal.md
Normal file
111
openspec/changes/archive/2026-01-05-add-gantt-view/proposal.md
Normal file
@@ -0,0 +1,111 @@
|
||||
# Proposal: Add Gantt View
|
||||
|
||||
**Change ID:** `add-gantt-view`
|
||||
**Issue Reference:** `FEAT-003` (issues.md)
|
||||
**Status:** Draft
|
||||
**Author:** Claude
|
||||
**Date:** 2026-01-05
|
||||
|
||||
## Summary
|
||||
|
||||
實作甘特圖視角,以時間軸方式呈現專案任務,顯示任務期間、依賴關係和里程碑。
|
||||
|
||||
## Motivation
|
||||
|
||||
甘特圖是專案管理的核心視覺化工具,可幫助團隊:
|
||||
- 了解任務時程與排程
|
||||
- 識別關鍵路徑
|
||||
- 發現資源衝突和瓶頸
|
||||
- 追蹤進度與延遲
|
||||
|
||||
目前系統僅有看板和列表視角,缺少時間軸視圖,無法直觀地規劃和追蹤專案進度。
|
||||
|
||||
## Scope
|
||||
|
||||
### In Scope
|
||||
- Backend: Task model 新增 start_date 欄位
|
||||
- Backend: TaskDependency model(前置任務關係)
|
||||
- Backend: 依賴關係 CRUD API
|
||||
- Frontend: Gantt chart 元件(使用第三方函式庫)
|
||||
- Frontend: 任務時程編輯(拖拉調整日期)
|
||||
- Frontend: 依賴關係視覺化(箭頭連線)
|
||||
|
||||
### Out of Scope
|
||||
- 關鍵路徑計算
|
||||
- 資源分配視圖
|
||||
- 基線對比功能
|
||||
- 匯出為圖片/PDF
|
||||
|
||||
## Design Decisions
|
||||
|
||||
### 任務依賴類型
|
||||
| Type | 說明 | 範例 |
|
||||
|------|------|------|
|
||||
| finish_to_start (FS) | 前置任務完成後才能開始 | 設計完成 → 開發開始 |
|
||||
| start_to_start (SS) | 前置任務開始後才能開始 | 設計開始 → 文件開始 |
|
||||
| finish_to_finish (FF) | 前置任務完成後才能完成 | 開發完成 → 測試完成 |
|
||||
| start_to_finish (SF) | 前置任務開始後才能完成 | 較少使用 |
|
||||
|
||||
**預設**: finish_to_start (FS) 為最常見類型
|
||||
|
||||
### Data Model 變更
|
||||
```sql
|
||||
-- Task 新增欄位
|
||||
ALTER TABLE pjctrl_tasks ADD COLUMN start_date DATETIME;
|
||||
|
||||
-- 新增依賴關係表
|
||||
CREATE TABLE pjctrl_task_dependencies (
|
||||
id UUID PRIMARY KEY,
|
||||
predecessor_id UUID REFERENCES pjctrl_tasks(id),
|
||||
successor_id UUID REFERENCES pjctrl_tasks(id),
|
||||
dependency_type ENUM('FS', 'SS', 'FF', 'SF') DEFAULT 'FS',
|
||||
lag_days INT DEFAULT 0,
|
||||
created_at TIMESTAMP
|
||||
);
|
||||
```
|
||||
|
||||
### 前端函式庫選擇
|
||||
建議使用 **DHTMLX Gantt** 或 **Frappe Gantt**:
|
||||
|
||||
| 函式庫 | 優點 | 缺點 |
|
||||
|--------|------|------|
|
||||
| DHTMLX Gantt | 功能完整、效能好 | 商業授權 |
|
||||
| Frappe Gantt | 開源、輕量 | 功能較少 |
|
||||
| React-Gantt-Chart | React 原生 | 社群較小 |
|
||||
|
||||
**建議**: 使用 Frappe Gantt(MIT 授權),足夠基本需求
|
||||
|
||||
### API 設計
|
||||
```
|
||||
# 依賴關係 API
|
||||
POST /api/tasks/{task_id}/dependencies # 新增依賴
|
||||
GET /api/tasks/{task_id}/dependencies # 取得依賴
|
||||
DELETE /api/task-dependencies/{dependency_id} # 刪除依賴
|
||||
|
||||
# 任務日期更新(使用現有 API)
|
||||
PUT /api/tasks/{task_id} # body 包含 start_date, due_date
|
||||
```
|
||||
|
||||
### 日期驗證規則
|
||||
- start_date 不可晚於 due_date
|
||||
- 有依賴關係時,根據 dependency_type 驗證日期合理性
|
||||
- 循環依賴檢測
|
||||
|
||||
## Affected Specs
|
||||
|
||||
| Spec | Change Type |
|
||||
|------|-------------|
|
||||
| task-management | MODIFIED (Multiple Views requirement 甘特圖細節) |
|
||||
|
||||
## Risks & Mitigations
|
||||
|
||||
| Risk | Mitigation |
|
||||
|------|------------|
|
||||
| 複雜依賴關係影響效能 | 限制單任務最多 10 個直接依賴 |
|
||||
| 循環依賴 | 新增/修改依賴時進行循環檢測 |
|
||||
| 大型專案載入慢 | 分頁載入或虛擬滾動 |
|
||||
|
||||
## Dependencies
|
||||
|
||||
- Frappe Gantt(或其他甘特圖函式庫)
|
||||
- 需要 Task model 已有 due_date 欄位(✓ 已存在)
|
||||