feat: implement custom fields, gantt view, calendar view, and file encryption

- Custom Fields (FEAT-001):
  - CustomField and TaskCustomValue models with formula support
  - CRUD API for custom field management
  - Formula engine for calculated fields
  - Frontend: CustomFieldEditor, CustomFieldInput, ProjectSettings page
  - Task list API now includes custom_values
  - KanbanBoard displays custom field values

- Gantt View (FEAT-003):
  - TaskDependency model with FS/SS/FF/SF dependency types
  - Dependency CRUD API with cycle detection
  - start_date field added to tasks
  - GanttChart component with Frappe Gantt integration
  - Dependency type selector in UI

- Calendar View (FEAT-004):
  - CalendarView component with FullCalendar integration
  - Date range filtering API for tasks
  - Drag-and-drop date updates
  - View mode switching in Tasks page

- File Encryption (FEAT-010):
  - AES-256-GCM encryption service
  - EncryptionKey model with key rotation support
  - Admin API for key management
  - Encrypted upload/download for confidential projects

- Migrations: 011 (custom fields), 012 (encryption keys), 013 (task dependencies)
- Updated issues.md with completion status

🤖 Generated with [Claude Code](https://claude.com/claude-code)

Co-Authored-By: Claude Opus 4.5 <noreply@anthropic.com>
This commit is contained in:
beabigegg
2026-01-05 23:39:12 +08:00
parent 69b81d9241
commit 2d80a8384e
65 changed files with 11045 additions and 82 deletions

View File

@@ -0,0 +1,68 @@
from sqlalchemy import Column, String, Integer, Enum, DateTime, ForeignKey, UniqueConstraint
from sqlalchemy.orm import relationship
from sqlalchemy.sql import func
from app.core.database import Base
import enum
class DependencyType(str, enum.Enum):
"""
Task dependency types for Gantt chart.
FS (Finish-to-Start): Predecessor must finish before successor starts (most common)
SS (Start-to-Start): Predecessor must start before successor starts
FF (Finish-to-Finish): Predecessor must finish before successor finishes
SF (Start-to-Finish): Predecessor must start before successor finishes (rare)
"""
FS = "FS" # Finish-to-Start
SS = "SS" # Start-to-Start
FF = "FF" # Finish-to-Finish
SF = "SF" # Start-to-Finish
class TaskDependency(Base):
"""
Represents a dependency relationship between two tasks.
The predecessor task affects when the successor task can be scheduled,
based on the dependency_type. This is used for Gantt chart visualization
and date validation.
"""
__tablename__ = "pjctrl_task_dependencies"
__table_args__ = (
UniqueConstraint('predecessor_id', 'successor_id', name='uq_predecessor_successor'),
)
id = Column(String(36), primary_key=True)
predecessor_id = Column(
String(36),
ForeignKey("pjctrl_tasks.id", ondelete="CASCADE"),
nullable=False,
index=True
)
successor_id = Column(
String(36),
ForeignKey("pjctrl_tasks.id", ondelete="CASCADE"),
nullable=False,
index=True
)
dependency_type = Column(
Enum("FS", "SS", "FF", "SF", name="dependency_type_enum"),
default="FS",
nullable=False
)
lag_days = Column(Integer, default=0, nullable=False)
created_at = Column(DateTime, server_default=func.now(), nullable=False)
# Relationships
predecessor = relationship(
"Task",
foreign_keys=[predecessor_id],
back_populates="successors"
)
successor = relationship(
"Task",
foreign_keys=[successor_id],
back_populates="predecessors"
)